Illinois Mechanics Lien Act
770 ILCS 60/34
Section 34 - Written Demand For Suit.

Upon written demand of the owner, lienor, or any person interested in the real estate, or their agent or attorney, served on the person claiming the lien, or his agent or attorney, requiring suit to be commenced to enforce the lien or answer to be filed in a pending suit, suit shall be commenced or answer filed within 30 days thereafter, or the lien shall be forfeited. Such service may be by registered or certified mail, return receipt requested, or by personal service.


- Go to preceding Section - - Go Back to Table of Contents - - Go to next Section -



Notes about this Section

Source: P.A. 82‑618.