Section 6 - Completion Time for Work.

In no event shall it be necessary to fix or stipulate in any contract a time for the completion or a time for payment in order to obtain a lien under this act, provided, that the work is done or material furnished within three years from the commencement of said work or the commencement of furnishing said material.


- Go to preceding Section - - Go Back to Table of Contents - - Go to next Section -



Notes about this Section

Source: Laws 1903, p. 230.